We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.
The cookies that are categorized as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ...
Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.
Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.
Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.
Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.
Advertisement cookies are used to provide visitors with customized advertisements based on the pages you visited previously and to analyze the effectiveness of the ad campaigns.
Client : Wirral Borough Council – Lingham Primary School
Sector : Education
Service : Fire Alarm Installation
Location : Moreton, Wirral
In June 2021, Fieldway were awarded a contract by Wirral Borough Council to install a new Fire Alarm system at Lingham Primary School over the School Summer Holidays. This involved stripping out the existing fire alarm and commissioning the new system in line with manufacturer requirements.
We installed a Grade A L2 System with an Advanced MX Pro 5 Panel and Apollo detection throughout the school. The panel we provided offers extended 38-hour battery life, ensuring prolonged protection in the scenario of power failure.
The installation was overseen by Project Manager Mike Allen who managed the programme of works. During mobilisation a detailed programme was created and communicated to the engineers to ensure that all aspects of the delivery and on-site requirements were fully understood. The programme included set project milestones and we tracked the project progress through weekly site meetings to review targets.
To complete the works we utilised a team of four engineers. They were selected by Mike based on experience and geography. All Fieldway engineers are suitably qualified to work with equipment for all fire alarm manufacturers and are cross-inducted across multiple contracts to ensure we have sufficient cover. The lead engineer for this project was the designated quality supervisor, ensuring all works were completed to BAFE standards.
We completed all work in time for the recommencement of the school term and with full adherence to the specification requirements.